East Orange
Hospital
Phase 1 Summary:
-Lighting-
- Square Feet: 300,000
- # of Buildings: 3
- Total Construction Costs: $305,441.60
- Total Fixtures: 3,125
- Total Construction Time: 2 months
Phase 2 Summary:
-HVAC-Controls-Roof-
Prime Energy Services was subcontracted by Metro Energy
Solutions and Essex Valley Healthcare's East Orange General Hospital for the
installation of a new roof and HVAC system at the administration building
located at 33 Evergreen Place, East Orange.
The demolition portion of the
roof replacement started with removing a phenolic foam roof down to the base
roof material (steel). The HVAC equipment and associated ductwork were also
removed during the roof demolition. A new Firestone rubber membrane roof with a
10-year warranty was installed to replace the sprayed foam roof.
The installation of the new HVAC
consisted of the following equipment; five (5) rooftop units, one (1) 30 ton
unit, four (4) 25 ton units, twenty six (26) VAV units, five (5) VAV changeover
controls, ten (10) VAV bypass controls, one (1) tracker ATC panel, with all
required sensors and five (5) rooftop curbs. |